Fourth Circuit Holds Per-Se Rule Does Not Apply in Bid-Rigging Case

WHAT HAPPENED

A three-judge panel from the US Court of Appeals for the Fourth Circuit overturned an executive’s bid-rigging antitrust conviction, holding that the district court erred in applying the per se standard to the executive’s alleged bid-rigging conduct.

The executive, Brent Brewbaker, rigged bids between his former employer, Contech, and its distributor, Pomona Pipe Products. The Fourth Circuit found that while Contech and Pomona both submitted competing bids for North Carolina Department of Transportation (NCDOT) projects, and Contech coordinated with Pomona to make Contech’s bids slightly higher priced, this conduct could not be deemed inherently unlawful under prior precedent because the entities had a manufacturer-distributor arrangement and were not simply direct competitors. In particular, the Fourth Circuit noted that manufacturer-distributor relationships such as the one between Contech and Pomona do not inherently lead to anticompetitive harm and may enhance competition.

Therefore, given the kind of relationship Contech and Pomona had, the Fourth Circuit held that the district court should have analyzed the conduct under the rule of reason to weigh the competitive implications of the parties’ agreement and conduct.

BACKGROUND

  • Contech manufactured and sold aluminum products.
  • Pomona distributed Contech’s aluminum products and was Contech’s exclusive dealer in North Carolina.
  • NCDOT used a bidding process for aluminum structure projects throughout the state. These projects required both the aluminum product and the services to install the aluminum structures.
  • Contech, Pomona and a third company were the consistent bidders for the NCDOT projects.
  • When either Contech or Pomona won a bid for a project, each would fulfill its contract using the other’s supply or services. Pomona, therefore, served as Contech’s “dealer” with Contech supplying Pomona the aluminum it needed to use in the projects Pomona eventually won; vice versa, Pomona provided necessary services to Contech when Contech won a bid. Neither Contech nor Pomona could win a bid without the products or services of the other.
  • In 2019, Brewbaker took charge of Contech’s bidding for these NCDOT projects and began intentionally submitting losing bids to enable Pomona to win by first asking for Pomona’s total bid price and then adding a markup to Contech’s bid price before submitting the bid to NCDOT.
  • DOJ alleged that Contech and Pomona engaged in bid rigging because they directly competed against each other’s separate bids. Brewbaker and Contech were indicted for violating Section 1 of the Sherman Act and conspiracy to commit mail and wire fraud.
  • Contech pleaded guilty to bid rigging and one fraud count.
  • Brewbaker proceeded to trial, and the district court convicted him of bid rigging and five other fraud-related counts (which were not overturned by the Fourth Circuit), upon concluding that Contech and Pomona’s conduct fell squarely within the definition of antitrust “bid rigging” under Section 1 of the Sherman Act.

HOW THE DECISION WAS REACHED

  • The Fourth Circuit explained that the rule of reason standard is the default framework used to scrutinize most business practices under the antitrust laws. It weighs [...]

    Continue Reading



read more

Former Government Contractor Executive Convicted of Procurement Fraud

On February 1, 2022, a federal jury found a former engineering firm executive guilty of conspiring to rig bids and defraud the North Carolina Department of Transportation (NCDOT) of hundreds of public works contracts worth more than $23 million. From at least 2009 through fall 2018, Brent Brewbaker was responsible for crafting and submitting bids to NCDOT on behalf of Contech Engineered Solutions LLC, an engineering firm that makes products used in bridge construction, water drainage and other public works projects.

Read more here to learn how companies can minimize the risk that they are investigated by the Procurement Collusion Strike Force (PCSF).




read more

Government Contractor Pleads Guilty to Bid-Rigging and Procurement Fraud

On June 7, 2021, as part of the US Department of Justice’s (DOJ) continuing commitment to prosecuting cases where the government is a victim, a government contractor pleaded guilty to one count of bid-rigging and one count of conspiracy to commit mail and wire fraud in connection with the DOJ’s ongoing investigation into public works contracts for the North Carolina Department of Transportation (NCDOT).

Ohio-based Contech Engineered Solutions LLC (Contech) entered its plea of guilty before a federal judge in the US District Court for the Eastern District of North Carolina and was sentenced to pay a $7 million criminal fine. Contech was also ordered to pay an additional $1,533,988 in restitution to the NCDOT. Notably, the DOJ did not impose a term of probation on Contech because Contech agreed to improve its compliance program to prevent recurrence of anticompetitive conduct. Contech, however, is required to cooperate with the DOJ, including producing documents and making witnesses available for interviews or testimony.

Contech and its former executive were indicted in October 2020 on six counts of alleged bid-rigging, conspiracy to commit fraud and mail and wire fraud in connection with a decade-long conspiracy involving public works projects in North Carolina.

This prosecution highlights the DOJ’s ongoing commitment to the Procurement Collusion Strike Force (PCSF) and its efforts to scrutinize public procurements and combat collusion and related fraud in government contracting.

The PCSF has conducted extensive training of law enforcement officers and procurement officers, among others, to help identify scenarios and situations where collusion is more likely to occur. The PCSF is also utilizing data analytics to advance its investigations, building on technological advancements and more useable data sets to target and prosecute anticompetitive conduct.

Importantly, the PCSF has recently doubled in size and has gone global just as the United States has approved unprecedented stimulus spending in response to the global COVID-19 pandemic and as the Biden administration is poised to approve a new infrastructure plan. The PCSF has provided tools that allow any individual to report suspected collusion via email or an online tip center. Enforcers’ renewed commitment to procurement collusion—coupled with increased government spending—will likely lead to more investigations and additional prosecutions in 2021.

Contech, a manufacturer of aluminum and other products, conspired with its supplier in bidding on numerous NCDOT public works projects. According to the indictment, the former Contech executive would obtain (or direct his subordinate to obtain) the supplier’s total bid price in advance. Using that information, Contech then submitted bids to be intentionally higher than its supplier. The indictment also alleged that Contech submitted false certifications that its bids were competitive and free of collusion throughout the conspiracy.

The indictment alleged bid-rigging between a manufacturer and its supplier, which is typically a vertical relationship and generally subject to the Rule of Reason rather than per se criminal analysis. Under the Rule of Reason, antitrust enforcers balance the anticompetitive effects of the conduct in question against the procompetitive benefits. Certain anticompetitive conduct, however, [...]

Continue Reading




read more